MMA& PMMA New Material Forum is to be held on Jun 6th-7th 2024 in Suzhou, to explore and discuss MMA & PMMA new material industry policy & market trend, art of the date process & commercial progression, cost & environment protection competition power of different process routes, new project investments, MMA & up-/downstream integration, optical grade PMMA & other major downstream product planning, PMMA downstream application developed & recovery etc.

 

Recently, as reported by Panjin Release, Panjin Sanli CAS New Material Co Ltd 100kt/a new material production project would reach mechanical completion by the end of May.

 

Panjin Sanli CAS New Material Co Ltd president Yu Chunjian introduced that, “our project initiated construction in May last year and, as of the date, phase I project plant building, auxiliary production building, CCR, power distribution, analytical laboratory and more building units all have reached completion of construction on schedule, in addition to 95% of equipment installation. To realize mechanical completion by the end of May this year, we conducted a safety inspection and necessary job training before starting work as soon as possible after the Spring Festival. Immediately after the 15th day of the first lunar month, more than 260 workers entered the site for construction, to ensure that trial production can be conducted before the end of Jul.”

 

The project is a CNY1.1bn capital investment, to build 12,000Nm3/h gasification plant (12000Nm3/h gasification and 12000Nm3/h syngas refining units), 50kt/a MMA plant (MAL unit + MMA unit), 40kt/a n-propanol plant (80kt/a propyl-aldehyde unit + 40kt/a propanol unit + 40kt/a formaldehyde unit).